IT Corner Beverly Hills Fiber Construction
Construction
Construction Updates
One of the goals of the Beverly Hills Fiber build-out is to minimize disruption for our residents and businesses.  This is a complex and comprehensive construction project that will not be without its inconveniences, but we’re committed to making every effort to work smart and communicate effectively throughout the process. To that end, we are segmenting the city into grids of some 100+ micro-neighborhoods.  By focusing construction within a smaller footprint, we can get in and out more quickly with less irritation to residents. 

Construction Activities
September 2017- June 30, 2018
Coldwater Area (North of Sunset)

January 3rd - August 30, 2018
LaCienega Area- South East